Project management practice
Project management practice exercises with worked answers
Try a fictional delivery case, compare a schedule and sponsor update, then use a rubric to inspect your reasoning before practising in Project Mastery.
Your brief: the opening date is at risk
Fictional teaching case, separate from the platform’s graded exercises. An office-access rollout has a nine-working-day forecast and a day-11 commitment. Configuration is on the driving path and now takes three extra days. Budget is 20,000 units; actual spend is 12,000 and remaining cost is estimated at 10,000. No change has been approved.
Make three decisions before reading on
- State the forecast finish, commitment variance and remaining buffer.
- Write one risk or issue with an owner and next action.
- Write a three-sentence sponsor update with one decision and deadline.
Worked answer and reasoning
Forecast finish is day 12. Against day 11, that is one day late; the two-day buffer is consumed. The three-day configuration delay is a known issue, while uncertainty about rental availability is a risk. Forecast cost is 22,000 units, 2,000 or 10% over budget.
Example update: “Configuration delay moves forecast completion to day 12 against the day-11 baseline; cost forecast is 22,000 against 20,000. The delivery lead is validating a rental option and its effect on installation. Please decide by day 4 whether to fund the validated recovery option or accept the revised date; neither date nor budget baseline has yet changed.”
This answer does not assume rental will recover the day. It asks for validation and an authorised choice. A different option can be defensible if its assumptions and effects are clear.
Self-review rubric
| Criterion | What to look for |
|---|---|
| Schedule | Correct arithmetic and the baseline still visible. |
| Cost | Actual plus remaining cost, same basis, explicit variance sign. |
| Risk/issue | Known event separated from uncertainty; action owner named. |
| Decision | Options, authority and deadline; no invented approval. |
Continue with a different case
Do not memorise this answer as the platform answer key. The practice week uses the published Community clinic relocation exercises with their own briefs and rubrics. Read those inputs, submit your work and review the feedback.